Pleading Inconsistent Theories of Recovery

Written By: Randy J. Heller

03/23/18
court house

Bucking a recent trend, a lower court refused to dismiss potentially “duplicative” causes of action in a contractor’s complaint, allowing the contractor to assert both “legal” and “equitable” claims.

In 1987, the highest court in New York ruled that when one has a valid and enforceable written contract governing a particular subject matter, one may not ordinarily join similar claims arising out of the same subject matter. A quasi-contract only applies in the absence of an express agreement and is not really a contract at all, but rather a legal obligation imposed in order to prevent a party’s unjust enrichment. In essence, the court held that one cannot recover both in contract and in quasi-contract.
 
Since then, lower courts have regularly thrown out similar, non-contractual (“equitable”) causes of action (such as those based in quantum meruit, unjust enrichment, fair and reasonable value), where it is alleged that there was a written contract between the parties to the litigation.
 
A certain tension was created by this decision in that New York is a state in which “pleading in the alternative” is both permitted and encouraged. In a classic example of this, you are permitted to plead (e.g., in defense to a claim that you broke someone’s table) that (a) the table is not broken, and (b) the table was already broken when they gave it to you. The fact that these defenses are mutually exclusive is not an impediment to asserting them both in a pleading—so long as you pick one theory before trial.
 
However, in March Donaldson Interiors, Inc. v. Cauldwell-Wingate Co., LLC, Donaldson (the subcontractor) sued Cauldwell-Wingate (the contractor) for extra work balances, among other things. Because some of the extra work claims lacked a written change order, Donaldson sued both on theories of breach of contract, as well as in quantum meruit and for unjust enrichment. Cauldwell-Wingate sought to dismiss the equitable claims as duplicative of the breach claim, citing the 1987 Court of Appeals case.
 
The Supreme Court judge denied the motion to dismiss those causes of action, stating that while Donaldson may have to choose between them at some later point (certainly by trial, or even on a summary judgment motion which is the “procedural equivalent of a trial”), it did not have to do so in its pleading. Where there were questions of fact regarding whether the express contract was altered by the parties’ course of conduct (with respect to the treatment of extra work), it could not be determined to what extent the contract applied to the dispute.
 
Accordingly, the court held that the equitable causes of action could survive a motion to dismiss at the early stages of the litigation. In short, one could plead both, but not recover on both.
 
One hopes this will stem the tide of seemingly knee-jerk dismissals of “duplicative” equitable causes of action at the pleading stage.

Read more articles authored by attorneys in our Construction Law Practice or continue browsing the Construction Law Blog.
 

about the authors

Randy J. Heller

Partner

For over forty years, Mr. Heller has specialized in construction law and litigation, representing some of the largest and most successful contractors in the nation.

View Profile